Engineering
T/W H Reconstruction (H4-H7)
Project starts: 5/19//2008
Completion date: 10/20/2008
Estimated budget: $4,633,738
Monthly Updates:
1/9/08 - This project will reconstruct T/W H from H4 to H7. A 90% design review meeting is scheduled for January 9, 2008.
3/31/08 - This project will reconstruct T/W H from H4 to H7. The bid opening for this project is scheduled for April 16, 2008.
5/13/08 - The bid opening for this project was held on April 16, 2008. The apparent low bidder is Granite Construction. An administrative notice to proceed will be issued on May 19, 2008.