Engineering

International Terminal Modifications

Project starts: 1/28/2007
Completion date: 5/21/2008
Estimated budget: $2,091,000

Monthly Updates:
1/09/08 - Garff Construction was the apparent low bidder for this project. Contract documents are being executed.

3/31/08 - The Contractor has completed approximately 85% of the steel framing.  Interior dust walls have been constructed. The store front has been removed.

5/13/08 - The Contractor has completed 100% of the roof framing. The conveyor installation at the EDS is ongoing and is approximately 70% complete. Substantial completion is anticipated for June 21, 2008.