Cooling Tower Replacements for Chillers 1, 2, and 3

Project starts: 2/28/2008
Completion date: 5/30/2008
Estimated budget: $508,000

Monthly Updates:
1/09/08 - Garff Construction was the apparent low bidder for this project. Contract documents are being reviewed.

3/31/08 - The Contractor has completed the demolition.  The new tower was delivered to the airport on March 2, 2008.  Boring for the caissons began on Monday, March 24, 2008.

5/13/08 - The tower was operational as of April 29, 2008.  Final change order work is currently being processed.  The final walkthrough is scheduled for May 16, 2008.