Cooling Tower Replacements for Chillers 1, 2, and 3
Project starts: 2/28/2008
Completion date: 5/30/2008
Estimated budget: $508,000
Monthly Updates:
1/09/08 - Garff Construction was the apparent low bidder for this project. Contract documents are being reviewed.
3/31/08 - The Contractor has completed the demolition. The new tower was delivered to the airport on March 2, 2008. Boring for the caissons began on Monday, March 24, 2008.
5/13/08 - The tower was operational as of April 29, 2008. Final change order work is currently being processed. The final walkthrough is scheduled for May 16, 2008.