Engineering
T/W Q Centerline Lights & Overlay
Project starts: 11/29/2007
Completion date: 2/06/2008
Estimated budget: $2,131,000 (Engineer's Estimate)
Monthly Updates:
1/9/08 - This project will install taxiways in-pavement centerline lights and rehabilitate the pavement surface on T/W Q. A 90%
design review meeting is scheduled for January 16, 2008.
3/31/08 - This project will install taxiway in-pavement centerline lights and rehabilitate the pavement surface on T/W Q. This project was submitted to the FAA for review and approval on February 29, 2008.
5/13/08 - This project will install taxiway in-pavement centerline lights and rehabilitate the pavement surface on T/W Q. This project was submitted to the FAA for review and approval.