Engineering

Terminal Signage Modifications (TU1 and TU2)

Project starts: 3/17/2008
Completion date: 6/13/2008
Estimated budget: $83,679

Monthly Updates:
10/08/07 - This project will modify the passenger way-finding signage in Terminal 1 and Terminal 2. Work will include modifying
existing sign faces, relocating existing signs, and installation of new signs. The 90% review meeting for this project is scheduled for October 18, 2007.

1/09/08 - This project will modify the passenger way-finding signage in Terminal 1 and Terminal 2. Work will include modifying
existing sign faces, relocating existing signs, and installation of new signs. Bid documents will be available to the public on January 21, 2008.

3/31/08 - This project will modify the passenger way-finding signage in Terminal 1 and Terminal 2.  Work will include modifying existing sign faces, relocating existing signs, and installation of new signs.  The apparent low bidder is Young Electric Sign Company.  Contract documents are being executed.

5/13/08 - A construction notice to proceed for this project was given to Young Electric Sign Co. on April 2, 2008.  The airport is waiting for shop drawings to be submitted by the Contractor.