Engineering
Tooele Valley Apron Expansion
Project starts: 3/24/2008
Completion date: 8/30/2008
Estimated budget: $456,144
Monthly Updates:
3/31/08 - This project will relocate the existing fuel island and expand the existing apron area by approximately 44,0000 square feet to provide additional parking for aircraft. The apparent low bidder for this project is DRD Paving. A pre-construction meeting was held on March 20, 2008. The Contractor was given notice to proceed on Monday, March 24, 2008.
5/13/08 - The Contractor is currently constructing the new apron. The fuel tank and pad have been relocated but are not operational due to pending electrical work.