Engineering
Potable Water Cabinets
Project starts: 5/09/2008
Completion date: 10/31/2008
Estimated budget: $1,149,500
Monthly Updates:
3/31/08 - The Utility Master Plan continues into final document stage as the first phase of infrastructure begins. The recommended first phase of infrastructure will provide civil utility services to the first new bank of potential hangars located north of the existing development adjacent to Taxiway A. The scoping and first design review meetings will be scheduled for the first week in April.
5/13/08 - A construction notice to proceed for this project was given to Garff Construction on May 9, 2008.
6/11/08 - The contractor was given a construction notice to proceed on May 9, 2008. Permits have been obtained and the cabinet shipping was received. Installation work began on June 11, 2008.