Engineering
Concourse E Elevator
Project starts: 6/03/2008
Completion date: 12/05/2008
Estimated budget: $725,800
Monthly Updates:
3/31/08 - The Utility Master Plan continues into final document stage as the first phase of infrastructure begins. The recommended first phase of infrastructure will provide civil utility services to the first new bank of potential hangars located north of the existing development adjacent to Taxiway A. The scoping and first design review meetings will be scheduled for the first week in April.
5/13/08 - The bid opening for this project was held on May 7, 2008. The apparent low bidder is Zwick Construction. Contract documents are being executed.
6/11/08 - The contractor was given a construction notice to proceed on June 3, 2008. Shop drawings are currently being prepared.