Engineering
Asphalt Overlay Program Phase IV
Project starts: 06/09/2008
Completion date: 09/06/2008
Estimated budget: $842,466
Monthly Updates:
3/31/08 - The Utility Master Plan continues into final document stage as the first phase of infrastructure begins. The recommended first phase of infrastructure will provide civil utility services to the first new bank of potential hangars located north of the existing development adjacent to Taxiway A. The scoping and first design review meetings will be scheduled for the first week in April.
5/13/08 - The project will construct and/or overlay the following areas: The loading dock area and parking lot of the warehouse at the International Center, the overflow parking lot bus lane, and the passenger drop-off lane of Terminal Drive. The bid opening for this project is scheduled for May 14, 2008.
6/11/08 - The contractor was given a construction notice to proceed on June 9, 2008.