Engineering
Continental Reservation Center Demolition
Project starts: 6/03/2008
Completion date: 7/18/2008
Estimated budget: $90,000
Monthly Updates:
3/31/08 - The Utility Master Plan continues into final document stage as the first phase of infrastructure begins. The recommended first phase of infrastructure will provide civil utility services to the first new bank of potential hangars located north of the existing development adjacent to Taxiway A. The scoping and first design review meetings will be scheduled for the first week in April.
5/13/08 - The apparent low bidder is Bird Construction. Contract documents are being executed.
6/11/08 - The contractor was given a construction notice to proceed on June 3, 2008. Mobilization is complete and the application for the air quality permit has been submitted.