PROJECT ELEMENTS

HERE'S WHAT THE NEW SLC WILL INCLUDE

 

 

2013

 

 

Begin terminal design process

Begin rental car facilities and parking garage design process

 

2014

 

 

Rental car facilities construction begins

 

2015

 

 

Rental car facilities complete

Begin construction of terminal and west concourse

 

2016

 

 

Parking garage construction begins

 

2017

 

 

Begin construction of terminal roadway system

 

2018

 

 

Open new terminal, west concourse and parking garage

Demolish Terminals 1 and 2 and existing parking garage

Begin construction of east concourse

 

2019

 

 

 

 

2020

 

 

Occupy gates on south side of east concourse

 

2021

 

 

Demolish International Arrivals Building and rebuid connector to Concourse D

Demolish Concourse A

 

2022

 

 

Occupy gates on north side of east concourse

 

2022-2026

 

 

Renovate existing Concourses B, C and D

Economic impact (info to come)

Public opinion survey results (info to come)

FAQs (written and video)

Environmental Assessment info (link to EA)

News and updates