Runway 16L-34R Pavement Rehabilitation

Project starts: 04/01/2013
Completion date: 07/06/2013
Estimated budget:  $11,556,192

Monthly Updates:

9/11/12
The bid opening for this project was held on August 29, 2012. The apparent low bidder is Granite Construction. Contract documents are being prepared.

10/11/12
No update.

11/6/12
The bid opening for this project was held on August 29, 2012. The apparent low bidder is Granite Construction. Contract documents have been executed.

1/10/13
An administrative notice to proceed for this project was issued on December 13, 2012. The Contractor is currently submitting documents for the badging process and preparing submittals to the Airport for review and approval.

2/14/13
No update.

3/14/13
An administrative notice to proceed for this project was issued on December 13, 2012. The Contractor is currently submitting documents for the badging process and preparing submittals to the Airport for review and approval. A construction notice to proceed is scheduled for March 20, 2013.

4/10/13
A construction notice to proceed was issued to the Contractor on April 1, 2013. The runway was closed on April 1 and will remain closed for 60 calendar days. Following this closure, the runway will open for day use for 30 calendar days while the lighting system is reinstalled.

05/08/13
No update.

6/20/13
The runway opened for daytime use on June 5, 2013. The runway remains closed at night while the lighting system is being reinstalled by the Contractor.

9/12/13
Substantial completion for this project was issued on July 6, 2013. The contractor is currently working on punch list items.

 

Space for Lease

SLCIA Space for Lease

Find information about available space for lease at Salt Lake City International Airport.


Fast Facts

SLCIA Fast Facts

Fast facts on Salt Lake City International Airport.