North Support Fuel Island Improvements

Project starts: 04/10/2014
Completion date: 5/29/15
Estimated budget: $674,050

Monthly Updates:

01/08/14
This project will provide improvements to SLCDA's fueling facility located in the North Support area of the airport campus. Work will include replacing the old fuel dispensers (gasoline and diesel), adding an additional diesel fuel dispenser, and modifying the pumps in the underground diesel storage tanks to increase the delivery flow rate. A mandatory pre-bid meeting was held on January 6, 2014. The bid opening for this project will be held on January 22, 2014.

2/13/14
This project will provide improvements to SLCDA's fueling facility located in the North Support area of the airport campus. Work will include replacing the old fuel dispensers (gasoline and diesel), adding an additional diesel fuel dispenser, and modifying the pumps in the underground diesel storage tanks to increase the delivery flow rate. The bid opening for this project was held on January 22, 2014. Bids are currently being evaluated.

3/13/14
This project will provide improvements to SLCDA's fueling facility located in the North Support area of the airport campus. Work will include replacing the old fuel dispensers (gasoline and diesel), adding an additional diesel fuel dispenser, and modifying the pumps in the underground diesel storage tanks to increase the delivery flow rate. The bid opening for this project ws held on January 22, 2014. The apparent low bidder is Granite Construction. Contract documents are currently being prepared.

05/14/14
This project was awarded to Granite Construction. An administrative notice to proceed was given to the Contractor on April 10, 2014. A construction notice to proceed will be issued when the fuel dispensing equipment arrives on the project site. The delivery date of the equipment is anticipated for June 14, 2014.

07/31/14
An administrative notice to proceed was given to the Contractor on April 10, 2014. A construction notice to proceed will be issued when the fuel dispensing equipment arrives on the project site. The delivery date of the equipment is anticipated for September 15, 2014.

09/11/14
An administrative notice to proceed was given to the Contractor on April 10, 2014. A construction notice to proceed will be issued when the fuel dispensing equipment arrives on the project site. The delivery date of the equipment is anticipated for October 15, 2014.

11/7/14
An administrative notice to proceed was given to the Contractor on April 10, 2014. A construction notice to proceed was scheduled to be issued when the fuel dispensing equipment arrives on the project site. Due to the long lead time for the fuel dispensing equipment and the winter weather approaching, a decision was made to postpone the installation of the equipment until April of 2015.

Space for Lease

SLCIA Space for Lease

Find information about available space for lease at Salt Lake City International Airport.


Fast Facts

SLCIA Fast Facts

Fast facts on Salt Lake City International Airport.