Construction Projects
Escalators to Terrace Restaurant
Project starts: 11/07/2011
Completion date: 3/08/2012
Estimated budget: $371,757
Monthly Updates
9/15/22
This project will include installation of new escalators from the concourse level to the third level restaurant in Terminal 1 as well as removal of the existing solid wall on the northeast perimeter of the restaurant area and replacing the solid wall with a glass railing to increase visibility to the restaurant level. Other work will include rerouting of utilities and modifying building services as required to support the new concessions program.
10/13/11
This project will include installation of new escalators from the concourse level to the third level restaurant in Terminal 1 as well as removal of the existing solid wall on the northeast perimeter of the restaurant area and replacing the solid wall with a glass railing to increase visibility to the restaurant level. Other work will include rerouting of utilities and modifying building services as required to support the new concessions program. The bid opening for this project will be held on October 12, 2011.
11/9/11
A pre-construction meeting was held on November 3, 2011. A notice to proceed was issued at that time. The Contractor is currently going through the badging process. Shop drawings are being submitted for procurement of equipment and materials.
2/9/12
The escalators have been installed and anchored to the mezzanine and third level restaurant. The escalator railing and landing decks are being constructed. The project is approximately 70% complete.
3/14/12
This project is substantially complete. The Contractor is currently working on punch list items.